WRW Construction Ltd

Project Name: WRW Construction Ltd

Contract Duration: 12 Weeks

Completion Date: February 2019

The former Custom House and York Hotel buildings in the center of Cardiff were redundant for a number of years prior to planning approval for a 20 storey Premier Inn hotel, with bar and restaurant.

Bond Demolition Ltd worked closely with WRW during the tender period taking account of the development proposals to ‘sensitively redevelop’ Custom House, retaining its listed façade, and bringing it back into productive use. The York Hotel site was demolished.

All works were undertaken ‘in-house’ including licensed asbestos removal,  the strip out of internal fixtures and fittings, forming of internal openings to facilitate the erection of the façade retention system. Subsequently the hand and mechanical demolition could be completed in and around the support structure, followed by uplifting of slabs and foundations and removal of demolition arisings offsite to a licensed facility.

KEY ELEMENTS

  • Asbestos removal as positively identified in the survey
  • Soft strip and removal of loose materials
  • Create openings in order to facilitate the façade retention
  • Forming concrete bases to receive the support framework
  • Hand and mechanical demolition using a hi-reach rig

CHALLENGES

  • City center working
  • Space constraints of site
  • Hi-Reach demolition
  • Deliveries in and out during specific times
  • Proximity of the main railway line
  •  
  •  
  •  

Some of Our Projects

Watermore Infants School

Location: Woodend Rd, Frampton Cotterell, Bristol

Contract Duration: 10 Weeks

Completion Date: October 2022

Pencoedtre High School

Location: Merthyr Dyfan Road, Barry

Contract Duration: 20 Weeks

Completion Date: June 2022

South Gloucestershire Council

Location: Charborough Road, Bristol

Contract Duration: 28 Weeks

Completion Date: September 2019